As Lockheed Martin prepares to release the first F-35 Block 4 software updates this summer, the company and the Joint Program Office are already well into analyses that will decide what will comprise Block 5 and later upgrades, Lockheed’s F-35 program manager said. For now ...
Declaring “full rate production” for the F-35 may come in early 2024, but the declaration may be moot, as the jet is already being built at nearly its maximum planned rate, Program Executive Officer Lt. Gen. Michael J. Schmidt said.
More delay may be in store for the TR-3 update of the F-35 fighter, program executive officer Lt. Gen. Michael Schmidt told Air & Space Forces Magazine. Test resources, software lab capacity, and too much concurrency have put the effort at least two years behind ...