The F-35's program director promised Congress an F-35 sustainment strategy this summer, but said it's unlikely he'll achieve the elusive goal of $25,000 cost per flying hour by 2025. Negotiating three one-year sustainment deals is a "carrot" to get a better deal from Lockheed Martin ...
A Pentagon declaration that the F-35's initial development is complete is still months away, but even when it comes, it won't trigger a surge in production of the fighter. “I don’t think you’ll see a large deviation” in production when full-rate is declared, according to ...
An independent academic team will assess how ready the F-35 is for full-rate production, and its findings will be integrated into a new program timeline, the Joint Program Office reported. The move follows a full-rate production delay by Pentagon acquisition and sustainment chief Ellen M. ...
The F-35 will miss yet another deadline for completing final tests and being approved for full-scale production, according to a memo from Pentagon acquisition and sustainment chief Ellen Lord. The sticking point is integration of the F-35 with a wargaming simulation system. This has gone ...
Secrecy prevents the F-35 Joint Program Office from revealing the corrective measures being taken after hardware and software deficiencies contributed to a May crash of an F-35 at Eglin Air Force Base, Fla., the JPO said Nov. 23. It is unusual for the government to ...
The Air Force's major acquisition programs collectively increased in cost $3.7 billion in the first quarter of fiscal year 2020, according the Pentagon's latest Selected Acquisition Reports. Most of the increases were due to buying more units and services. The F-15 Eagle Passive Active Warning ...
Excessive landing speed was the primary cause of the May 19 crash of an F-35A at Eglin Air Force Base, Fla., though faulty flight control logic, the helmet mounted display, the jet's oxygen system, and improper training and were all contributing factors, according to an ...
Due to pandemic-related slowdowns, Lockheed Martin expects to deliver 122 F-35s in calendar year 2020—20 less than planned, company executive vice president for aeronautics Michele A. Evans said in a Sept. 9 interview. The tally will be gradually made up over two years, in order ...
House lawmakers hammered Lockheed Martin for persistent problems in the F-35 Joint Strike Fighter enterprise during a July 22 hearing, as the defense giant declined to promise it would fully reimburse the Pentagon for defective equipment files. At issue are electronic equipment logs, which act ...
The Air Force's F-35A fleet has become its third-largest fighter fleet—larger than that of the F-15C/D or E variants and larger than the F-22 Raptor fleet—and the type will likely surpass 250 air frames by the end of August, according to the Joint Program Office. ...
Parts delays and the need to keep workers appropriately separate will translate to an 18-24 airplane shortfall in Lockheed Martin's planned 2020 F-35 production, the company said May 19. The figure is a worst-case estimate and could be mitigated by an earlier acceleration of parts ...
Flight testing of the F-35 and other aircraft has been paused at Edwards Air Force Base, Calif., due to the COVID-19 pandemic. However, Pentagon acquisition and sustainment chief Ellen Lord declined to say whether this will delay the F-35's full-rate production decision, which is expected ...