The 301st Fighter Wing in Fort Worth, Texas, became the first standalone Reserve unit in the Air Force to get its own F-35s, welcoming the first fighter Nov. 5.
Lockheed Martin is making good on predictions that it can deliver F-35 fighter jets at a rate of 20 per month, helping clear a backlog created by a yearlong hold on deliveries that was lifted in mid-July.
It'll take up to 18 months for Lockheed Martin to deliver the 100 or so F-35s that went directly from production line to storage, awaiting the completion of Tech Refresh 3 testing. Customers haven't complained about the order in which the backlog is being delivered.
The Air Force would only bed down 25 F-35s in fiscal 2026 under a plan included in a recent Pentagon report on the fighter. The plan calls for the service to field some 700 of the jets by the end of the decade and never ...
Two newly manufactured F-35s touched down at the home of the 301st Fighter Wing in Texas last week, as the wing is transitioning from its F-16 fleet to the fifth-generation aircraft. But the jets are not there to stay; the F-35s that arrived at Naval ...
Lockheed Martin began delivering F-35s again on July 19, after a year of building the fighters and putting them directly into storage because their Tech Refresh 3 systems and software were not fully tested.
More than 90 brand-new F-35s, many in storage since last fall, can be delivered now that a “truncated” version of the Tech Refresh 3 software has been approved for use.
Due to the prolonged delay in deliveries of the Tech Refresh 3 version of the F-35 fighter, Denmark is pulling six of its TR-2-configured F-35 jets stationed in the U.S. back to home base in order to consolidate aircraft and get better training for its ...
Newly-built F-35s that have been stacking up in storage could start to be delivered as soon as July, assuming a “truncated” Tech Refresh 3 software package is stable and safe enough for operational crews, the Joint Program Office said.
So many new F-35s have piled up waiting for TR-3 upgrade testing to conclude that it will take a year to deliver them all once deliveries get the green light to resume, according to a new Government Accountability Office report. That go-ahead isn't likely to ...
Lockheed Martin may not resume deliveries of the F-35 until this summer, but international partners and the Joint Program Office are looking at accepting aircraft earlier, without full validation of the Tech Refresh 3 upgrade.
The first F-35s with the Tech Refresh-3 upgrade—largely a processor upgrade upon which the Block 4 configuration of the fighter will ride—will be delivered before the middle of next year, a Lockheed Martin spokesperson said Sept. 6. But that will have an impact on Air ...