Operational testing of the MH-139A Grey Wolf helicopter could be delayed if all the necessary fixes to the system aren’t made in time, the Pentagon’s Director of Operational Testing said. Dust ingestion, gun issues, software, and the intercom are among the problems to be ironed ...
Hundreds of test flight hours Boeing flew in prototype T-7A trainer aircraft cannot be used to assess the system’s operational effectiveness or suitability because the design has changed so much, the Pentagon’s top test official said recently. Instead, the Air Force’s plans to buy extra ...
The KC-46A Pegasus aerial tanker still isn’t meeting required mission capable rates, mostly due to parts shortages, and other significant problems are still being remedied, the Pentagon’s test director said in a new report.
The new F-15E and F-15EX electronic warfare suite, meant to protect the fourth-generation fighters in contested battlespace—was shown to be “operationally effective” and “suitable,” the Pentagon's Director of Operational Test and Evaluation said.
The F-35 fighter program continues to struggle with meeting test milestones and mission readiness goals, but progress is being made on both fronts, according to the latest report from the Pentagon’s test director and comments from the Joint Program Office and Lockheed Martin.
While the Pentagon’s chief weapons tester continues to have concerns about the MH-139 helicopter, the Air Force is on the verge of finishing developmental testing of the aircraft and fielding it at Malmstrom Air Force Base, Mont.; and Maxwell Air Force Base, Ala. The Grey Wolf ...
The Air Force's AGM-183A ARRW hypersonic missile is outrunning its test plan and evaluation tools, and the Air Force needs to get a test plan approved by the Director of Operational Test and Evaluation to assure the weapon delivers what's needed, the DOT&E said.
The Air Force’s new MH-139 Grey Wolf helicopter is at risk of not meeting “operational effectiveness requirements,” the Defense Department's chief weapons tester declared in a new report. Problems with the automatic flight control system, sensor display, and intercom system, along with its cabin layout and “restrictions ...
The Air Force should work closely with the Army, Navy, and Defense Department to identify best practices and share data as it looks to get its hypersonic missile program back on track, according to the recommendations of a new Pentagon report released Jan. 27. The AGM-183A ...
The Air Force has officially delayed the KC-46’s full-rate production decision milestone until 2024 as the next-generation tanker works through problems plaguing its Remote Vision System, the service announced June 8. The Air Force and the Pentagon’s Director of Operational Test and Evaluation decided the ...
Boeing has incurred another $148 million in losses for its KC-46 tanker program due to higher than expected manufacturing costs, as the company works with the Air Force to address continued deficiencies in the tanker’s capabilities. The company disclosed the losses in a Jan. 31 ...